Visit "Where can I get vaccinated" or call 1-877-COVAXCO (1-877-268-2926) for vaccine information.

1

Capital Improvement Projects

2024

Berkeley is scheduled to finish the last Denver Water project which will be installed by Denver Water sometime in the spring/summer of 2024. Berkeley is investing in a master plan so that any future capital improvements are identified.

2023

Insituform lined 4,415 linear feet of clay pipe sewer mains which will result in pipes that will have a life of over 75 years. Insituform also lined 3 manholes so there would be no infill or infiltration which will cut down on the flows and loadings Berkeley sends to Metro Water Recovery. Berkeley also invested in a hydraulic study to understand how much waste water is in Berkeley's mains to determine where Berkeley needs to invest in the future.

2022

Vortex has one remaining capital improvement to install in the 1st quarter of 2022. They will be installing a pressure reducing valve near 54th and Lowell. This will allow Denver Water to create a pressure zone because a pressure reducing valve is installed near 54th and Tennyson which allows them to maintain the pressure in the water main loop between the two pressure reducing valves.

Berkeley's Board also approved capital improvement funds to repair a sewer main near 54th and Sheridan which produces alot of groundwater infiltration. The Board has awarded Insituform a contract to install cured in place pipe to repair the sewer main and stop the infiltration. Staff will continue to look for sewer mains in poor condition and will refer to the Board for any action.

2021

Berkeley's Board approved the remaining capital improvement projects in accordance to the agreement between Denver Water and Berkeley to become a Total Service with Improvement District. A Notice to Bidders was placed in the Westminster Window on October 1 and October 8, 2020. Vortex was awarded the bid and began the project in 2021.

2020

There were no capital improvements done in 2020.

2019

There were no capital improvements done in 2019.


2018

In order to become a Total Service with Improvement District under Denver Water, Berkeley must complete water capital improvements in 2018. Once a schedule has been established, we will inform you of how you may be impacted by the construction.


2017

There are no scheduled capital improvements for 2017.


2016

There are no scheduled capital improvements for 2016.


2015

Berkeley's Board established capital improvements needs at their Board meeting in February 2015. One improvement is a pressure reducing valve on Tennyson Avenue near 54th Street. Berkeley has also been working with Hyland Hills Parks and Recreation and has an agreement with them to put in a 12" line looping it from Tennyson Street to Lowell Boulevard. This will improve the water quality and pressure. A bid document was placed in the Daily Journal and Westminster Window in their May 7, 14, and 21st editions for the PRV in Tennyson, to upgrade a section of pipe in Tennyson from 8" to 12", one point repair, and six full linings. All sealed bids were received by Martin/Martin on June 8th. The Board will have 60 days to determine which contractor will be awarded the project.